Sunday, 25 September 2016
update - ceiling of first floor.
This was yesterday's update.
The ceiling slab has been cast today.
Sunday, 18 September 2016
First Floor lintel level
Work is going on in satisfactory pace. now the first floor lintel level is completed.
All because of His blessings!
Monday, 12 September 2016
update -First Floor lintel level
First Floor lintel level on last saturday!
Monday, 5 September 2016
next phase
Last Sunday was the ceiling slab was cast. It rained heavily the next three days!
Now the pillars have started going up and the woodwork for the first floor is going on.
Tuesday, 23 August 2016
vaasakkaal
Perhaps coming Sunday we might cast the roof.
Tuesday, 16 August 2016
lintel sunshades lofts.....
Saturday, 6 August 2016
lintel level
As on 6 th Aug 2016